INDOOR PROJECT IN QATAR
FIFA World Cup 2022 in Qatar
World Cup Qatar 2022 Groups - Opponents are determined by draw. See the official website for details: FIFA WORLD CUP 2022™
Collaboration Process
Project Presentation
• Name: 2 set equipment for children's playrooms for the upcoming World Cup 2022 in Qatar.
• Location: project built at Hamad International Airport, Qatar (new airport and old airport).
• Project status: The project is still under construction and is expected to be completed on November 20, 2022.
• Project goal: Welcome to the World Cup in Qatar and bring joy to the upcoming 1,2 million visitors!
• Client plan: Two sets of indoor gaming equipment and interactive projection equipment have been installed at Qatar Airport.
• Project area: About 700 square meters. As shown in the picture, this is a photograph of the site sent to us by the customer.
Schedule of Communication of Two Parties
• July 4 2022 city Client contact usby accessing the site through a Google search. The customer said that due to the tight project cycle, the customer sent us photos of cases collected earlier. The customer asks if we can deliver in 2-3 weeks. Because in a few months the World Cup will begin.
• July 5 2022 city Beston A team of professional designers began to communicate with the designers of the Qatari investor. Its main communication purpose is to discuss the 2D layout.
• July 14 2022 city After about 10 days of communication, both parties basically decided on a 2D layout. During this time, we have undergone many optimizations and modifications.
• July 15 2022 city Beston received an advance from the customer and proceeded to 3D design. It is worth noting that the prepayment will be taken into account in the final settlement after confirmation of the final cooperation.
• July 25 2022 city After 6 rounds of design reviews, the 3D design was finally approved. The specific effect is shown in the figure.
Delivery and Shipping
• July 29 to August 1, 2022 On July 29, we signed an agreement with the customer to confirm the order. Then August 1st Beston Attractions LLC received customer's deposit.
• From August 2 to August 23, 2022 After receiving the deposit, we set about organizing production in the Chinese entertainment equipment factory. Execution of production work quickly within 20 days. Soon, around the 23rd, the construction of two sets of equipment for indoor children's play centers was completed. Then start preparing for shipping.
• From August 23 to September 25, 2022 On September 20, all equipment arrived at the port and customs clearance was completed. On September 25, all three containers were ready, and then we were going to send installers to supervise the installation work.
On site installation
• 10th of October 2022 To help Qatari customers complete the installation of children's entertainment center equipment and interactive projection at the new airport quickly and smoothly. Beston sent engineers with 20 years of experience to Qatar to installation manuals.
• 20th of October 2022 About 10 days later, a Beston engineer completed the on-site installation work at the new Hamad International Airport. Installation at Doha Airport is about 60 percent complete.
• November 20 2022 city The entire installation process is under control and runs smoothly. All installation work will be completed around November 20th. At this time, the first tourists of the World Cup will arrive.
Customer Reviews
• Individual design: During the communication, Beston learned about the general layout of our construction site and some potential needs, and Beston's sales manager very professionally suggested individual design. Beston's design team has also made many design optimizations.
• Professional advice: The Beston manager helps us think about the positioning of the project and the audience for which it is suitable. Because the equipment needs to be located in the international airport, Beston Amusement recommends the medium and high-end indoor playground equipment configuration for customers. This beautifully showcases the entire project and image.
• Reliable guidance: Although the epidemic is not over yet, Beston engineers overcame all obstacles and still went to Qatar to provide us with on-site installation guidance. Due to the tight deadlines for the delivery of the project, Beston engineers strictly controlled each link so that the equipment was delivered on time.
• Unity and cooperation: Throughout the process, the Beston team worked closely with our team to actively address the issues we encountered and provide suggestions. Leveraging the power of the generic Beston for our early installation. Regarding Beston's integration and cooperation process, we are very satisfied and highly appreciated.
Looking forward to more feedback
• More services: Beston provides more service and support. In addition, Beston can provide investment analysis and operations support for Qatari clients. We can provide plans on how to open, how to attract more traffic to the project, how to retain key customers and much more. Additional follow-up reviews will be continually updated on this page. Stay tuned!